Street Repairs Street Update Phase 2A Progress Day 5

3/13/2026

The first lift of aggregate base and the second lift is installed and has met the specification requirements for the compaction process. Some areas needed installation of Hot Mix Asphalt Concrete to meet requirements. The asphalt installation has been scheduled for Tuesday, March 17, 2026, and is subject to asphalt material availability.